• Succeeding in complicated construction disputes

    Succeeding in complicated construction disputes

    How to succeed in complicated construction disputes

    John FFF O’Brien, principal consultant at John Farage O’Brien, tells John Murphy how he generally succeeds for his claimant clients in more complicated construction disputes taken to mediation and conciliation — where the parties remain in control

    John Farage O’Brien, a well-established firm of contract claims and dispute consultants, has spent most of the past two decades providing an expert consultancy and support service to domestic and international construction clients.

    I asked principal consultant John FFF O’Brien how he achieves such success for his claimant clients in more complicated construction disputes, especially in areas where the parties still retain control of the process, at mediation and conciliation.

    John FFF O'Brien

    “We find that most adversarial groups we meet across the table normally possess an unbalanced weighting of knowledge and understanding across what we describe as the ‘four core construction industry disciplines’ and it is in the art of properly balancing the influences of these disciplines across the relevant facts we find resolution to many disputes.

    “We have often found this imbalance to have been driven, typically, by a single alpha personality group member, possessing limited knowledge of perhaps only one or two of the core disciplines. Typically, these would be an entrenched designer who on the one hand cannot put his/her buildable design intent on paper but on the other hand insists that the contractor should have priced it and built it, or an overly opinionated lawyer who should stick to conveyancing or a consultant expert of one sort or another who is not the expert he or she purported to be. They are normally the alphas who have been given ‘too much rein’ by their client!

    “This is where we often find our opponent’s weak point and naturally, that is the point where we will attack.”

    O’Brien explains that the four core construction industry disciplines that entwine into every construction dispute in different measures and weightings are (1) Commercial, (2) Contractual, (3) Legal and (4) Technical. Technical, he adds, is split into two sub-categories, Design and Construction Methodology.

    “Each discipline is but the tip of its own tall Christmas tree, with hundreds of branches spreading out below. Having to understand potentially thousands of underlying issues, enmeshed within all four disciplines is precisely what makes construction disputes inherently complex to assess and resolve, especially to those who are fluent only in one or two of the core disciplines (and whose fluency in those disciplines can often blind them to the importance of the others!).”

    “Conciliation or mediation is often the first time that the paying party on the other side of the dispute sees their position being rigorously stress-tested. In our experience, many such paying parties, having seen for the first time the limitations of their entrenched alpha team member, and realising how incomplete their grasp is of the four disciplines, begin to see the settlement as a much more attractive option.

    To get to a strong position of certainty before a dispute can be settled is an iterative process that requires constant input from a party’s team, which includes weighted inputs from witnesses of fact, experts, consultants and lawyers, says O’Brien.

    “The team needs to remain dynamic to react (and perhaps re-adjust its position) to the inevitable issue of new information from the opposition, by way of submission papers, pleadings, particulars, or from plenary sessions with the third-party neutral.”

    “The party receiving this new information needs to be receptive to objectively weighing its worth, and feeding results into a live risk register that is constantly updated to assess how the party’s position is either getting stronger or indeed getting weaker. A party with a clear and unjaundiced view of its own case’s strengths (and weaknesses!) will also do better in negotiation, as the scope for surprise and the need for rapid re-assessment is radically reduced.”

    I asked if similar considerations apply at adjudication or arbitration hearings.

    “As soon as parties enter into the arena of the short and sharp process of statutory adjudication under the Construction Contracts Act 2013, they have lost control of their dispute to a third-party neutral,” O’Brien points out.

    “Having your dispute crystallised and weighted objectively across the four disciplines, is paramount before pulling that trigger to refer. It is simply too late to do so for the first time under the quickfire demands of one of the Minister’s panel adjudicators, (using his/her powers and specialist knowledge to ascertain facts and matters in your case that are required for his/her decision in 28 days).”

    “If your dispute gets into the arbitration arena, then all party control is lost, and your fate now lies 100% in the hands of a third-party neutral, with very little scope for any further appeal or challenge – finding out your weightings at that stage is much too late.

    “Our advice is to get good advice early and remain in control,” O’Brien concludes.

    John FFF O’Brien, principal consultant at John Farage O’Brien, tells John Murphy how he generally succeeds for his claimant clients in more complicated construction disputes taken to mediation and conciliation — where the parties remain in control.

  • How I help people end disputes

    How I help people end disputes

    How I help people end disputes

    An interview with John O’Brien

    TO DISAGREE WITH SOMEONE is a healthy and very human thing to do, says John O’Brien during our interview. It is our differences in opinion that make us individuals, and this fosters conversation and debate.

    Where they do disagree, parties often discover that the facts and interpretations underlying their initial opinion may overlap but are seldom identical to those of the other. If we listen, learn and accept new facts and interpretations from each other, our opinions tend to change and we can come to an agreement on the subject matter, which is often quite different to what both parties understood when the initial disagreement occurred.

    Disputes occur when parties become entrenched or positioned in their opinion and tend not to be swayed by new facts or new interpretations.

    This is the stage at which John Farage O’Brien may be asked to intervene, either to advise one of the parties or, if both agree, to sit as their conciliator or mediator to help them find a way to settle their dispute.

    As John says: “At the core of every successful dispute resolution where parties have remained in control is a process where they have moved of their own accord from positional negotiation to principled negotiation, often with the assistance of a neutral third party.

    “Closing a dispute is of paramount importance to any organisation wishing to progress in its core activity or business. Across the globe, commercial organisations are now choosing to remain in control during dispute resolution by using mediation processes. These have now surpassed the traditional, adversarial route of litigation.”

    Closure is achieved primarily in two ways — one, where the parties themselves remain in control by assisted negotiation, mediation or conciliation and reach a settlement by agreement; and two, where the parties lose control and an arbitrator or judge finally decides the outcome for them.

    In fifteen years of resolving contractual disputes between public sector and private sector organisations, O’Brien has witnessed creative energies flowing backwards and forwards between well-organised parties fully engaged in a mediation process.

    John recalls: “Any willingness of both parties to investigate and then accept new facts and interpretations from each other, coupled with accepting changes to their initial opinions, was rewarded with successful early closure, settling the differences by agreement and avoiding a full-blown, time-consuming and costly dispute.”

    And the firm often has a hand in ensuring that early closure: “If the parties want us to act as the referee, whether as a conciliator, mediator, or arbitrator, in that case I, as principal consultant, will sit with the parties, and set out to manage the dispute to achieve a speedy and fair closure.”

    As only five per cent of arbitration hearings proceed to final award, and 95% of disputes are settled without recourse to arbitration, John is a major cheerleader for conciliation and mediation as the supreme forms of dispute resolution.

    Apart from their speed and relative simplicity, these forums have other advantages, the prime one being that the parties stay in control. As John says: “The success of mediation is rooted in a party’s ability to run its own live risk register from the outset, updated and recalculated when new facts or interpretations are discovered in the process. By doing so, that party creates its own opportunity to do something about it when the risks outweigh any potential rewards or success achieved by continuing in dispute.

    “Commercial organisations that are risk aware do not need to have judicial decisions imposed upon them. They are capable of deciding for themselves what is a sensible and reasonable settlement as the risk matrices unfold.

    “We’ve found that where parties failed initially to engage in mediation or conciliation, the dispute remained in a positional state which inevitably led to a judicial process. This usually meant an Arbitrator took full control and finally decided the outcome for the parties, sometimes years later.

    “In arbitration, a party’s energies are completely absorbed in an adversarial process that steals time and resources. Each party indulges in drafting pleadings, pursuing discovery and attending hearings, not to mention the enormous costs of lawyers, consultants and expert witnesses for both claimant and respondent.

    “It can be as expensive and time-consuming as a long court action,” John says.

    The sting in the scorpion’s tail comes two-fold, of course, in the form of the penal costs of interest added to any monetary award on the substantive issue and the successful party having its legal costs taxed by either the Arbitrator or the Taxing Master.

    And John points out: “Ironically, we have experienced parties that failed to engage fully in the first step, mediation or conciliation, only to find themselves battle-worn midway through an arbitration. They then mutually agree ‘time out’ to go right back into mediation, which becomes a parallel process in which settlement is reached and there is no return to arbitration.”

    Parties appearing before John O’Brien will have the benefit of his fifteen years of experience with construction disputes, his wide knowledge and legal expertise, and his expertise in and forensic knowledge of the construction sector. And more will undoubtedly be reaching out to him for that service, as there is now a requirement for public works contracts exceeding €10 million in value to have a named ‘standing conciliator’ included.

    “That’s a role that John Farage O’Brien are perfectly suited to,” says John, “and also in providing independent risk assessments, something that senior public sector decision-makers absolutely require.”

    “So, for those senior public sector officials who have not yet come across me in their dealings, I am very happy to offer a no-obligation consultation, whether in connection with appointing me as standing conciliator on a PWC or to obtain an independent risk assessment on the merits of a claim.”

    Those who engage John Farage O’Brien to mediate can be confident in their choice — but so also will the lucky party which engages John’s firm to advise or represent.

    He says: “We specialise in the construction sector, representing clients in dispute — contractors, construction professionals, public bodies such as local authorities, public procurement entities and PPPs. At ADR hearings, we advise and represent them, bringing to bear a wealth of experience both in dispute resolution and in commercial management, quantum, procurement, design, methodologies, project and programme management and the legal aspects of construction contracts.

    “We have handled cases totalling more than €2.5 billion in contract value since 2003, the vast bulk of which involved public sector bodies. When we advise a client —whether public body or contractor — we bring to bear an absolutely ferocious attention to detail, a forensic analysis of every element of every document, agreement, report, and act by either party.

    “Construction cases can be extraordinarily complicated, so our breadth and depth of experience here is key.”

    John is a Fellow of The Chartered Institute of Arbitrators (FCIArb, Dip.Arb.Law) and a practising CIF Arbitrator. He is a fully accredited Mediator with the Centre for Effective Dispute Resolution (CEDR). He is also a Chartered Quantity Surveyor (ASCS MRICS, BSc.Surv. Dip.Const.Econ), a Chartered Civil Engineering Surveyor (MCInstCES), a Construction Technician (Dip.Const.Tech) and a practising Conciliator on the CIF construction panel

    To disagree with someone is a healthy and very human thing to do, says John O’Brien in this interview. It is our differences in opinion that make us individuals, and this fosters conversation and debate.

  • Dissertation interview with John Farage O’Brien

    Dissertation interview with John Farage O’Brien

    Dissertation interview by Kate Hogan Final Year Quantity Surveying student in Bolton Street on Construction Adjudications in Ireland March 2024.

    Dissertation interview by Kate Hogan Final Year Quantity Surveying student in Bolton Street on Construction Adjudications in Ireland March 2024.

  • The Use and Misuse of Dispute Avoidance in Ireland

    The Use and Misuse of Dispute Avoidance in Ireland

    A paper presented to the Dispute Resolution Board Federation webinar 4th March 2021
    By NG Bunni

    Dispute Adjudication Boards were developed by FIDIC following the successful American experience of Dispute Review Boards and first appeared in the 1995 Orange Book for Design- Build and Turnkey projects. The Board’s function of “Review” was changed to “Adjudication” in order to simulate the Engineer’s Determination or Decision under the earlier editions of the FIDIC Forms.

    Following the successful use of Dispute Adjudication Boards, which I will now refer to as “DABs”, in the Orange Book, the function of a DAB was incorporated into the 1999 Red, Yellow and Silver Forms of Contract. However, in the Red Book, a Standing DAB was provided for, which related to a DAB being appointed for the duration of the entire project, whereas, in the Yellow and Silver Books, an adhoc DAB was provided for, which related to a DAB being appointed only after a dispute had arisen. The idea of an adhoc DAB was proven to be a mistake and was subsequently abandoned in the 2017 editions of the FIDIC Forms.

    In Ireland, the first Contract using the 1999 FIDIC Yellow Book and, thus a DAB, was the Dublin Light Rail Project, for short it is referred to as the “Luas”. Although this Contract used the Yellow Book, which provided for an adhoc DAB, the Employer’s lawyers had identified the mistake of using an adhoc DAB and instead, a Standing DAB was incorporated in this Project. The Project was designed as a fast public transport system for parts of the south of Dublin City and construction on the Project commenced at the end of 2001, with the Works being completed in September 2004. It had nine main Contractors and the Employer was known as the Railway Procurement Agency, the “RPA”. I was appointed as a sole Standing DAB for the duration of the Project. By the time it was completed, most of the problems faced were solved around the discussion table and only two disputes were referred to a full adjudication process. Arbitration was therefore not required to resolve any of the disputes that arose. This Project was taken to a second stage in February 2007, where the Rail Network was extended to part of the City Centre. The Employer continued to be the RPA and this second stage had only five main Contractors. Again, the same Form of the FIDIC Contract was used and I was, once again, appointed as a sole Standing DAB. The second stage of this Project was completed in March 2011.

    The combined cost of the two stages of this Project was over €700 million and, once again, all of the problems that arose were resolved through discussions and no arbitration was needed or instigated.

    During 2006/2007, the Irish Government had formed a Committee to adopt the use of the FIDIC Contracts in Ireland for construction projects. This was partly as a result of the success of avoiding arbitration in the Luas Project. We were just nearing the end of our work when the Irish Construction Industry was dealt a significant blow. The Committee was disbanded and we were informed that the relevant authorities had decided to use a new form of contract, which was later named as the Public Works Contract.


    On an article by Mr. John Farage O’Brien published in Construction News, February 2021.

    I was very fortunate that this article was published whilst preparing my presentation for this webinar. Mr. O’Brien is a prominent construction consultant in Ireland and, in his article, he lucidly explains the adverse effects of the PWCs on the Irish Construction Contracts scene, which, combined with two other events, he said created “the perfect storm”.

    The first version of the PWC was introduced in 2007 to replace the GDLA and the IEI Forms of Contract when, as Mr. O’Brien articulates, driven by a cost-saving effort, a ‘politician’s brief’ was developed. However, Mr. O’Brien explains that what many politicians at the time did not understand was that construction contracts are all about risk allocation and that the risk ought to remain with the party who is best placed to manage it in order to achieve commercial value. Failure to allocate a risk correctly can result in huge expense. Unfortunately, this absence of understanding of the nuances of risk allocation went unchecked and the PWC was introduced for all public works projects.

    Mr. O’Brien continued his explanation that the objective of the PWC was to ensure fixed lump sum contracts, which would provide cost certainty. Although the price of the tenders under this “new” form of contract were expected to be slightly higher than those tendered under the previous government contract forms, the objective of the PWC was that there would be no other costs attached to any project.

    Mr. O’Brien further explained that whilst the PWC’s fixed lump sum contract prices seemed great in theory, the politicians who initiated the drafting process did not fully grasp the mechanics of the Irish construction industry and that there were some very real problems with the PWCs. The first problem, as Mr. O’Brien correctly pointed out, was that these forms of contract were untried and untested, as nowhere in the World used forms such as these. Whereas the GDLA and IEI Forms of Contract were based upon their UK counterparts, meaning that parties to projects under these Forms of Contract could see that such contract worked in the UK, the entirely new PWC had no precedent from which parties could derive any interpretive certainty and this problem remains today. I would point out that this problem has been exasperated by the fact that the PWC has been amended no less than fourteen times since its inception.

    The second event that Mr. O’Brien refers to is the global financial crisis of 2008. This stunted any meaningful assessment of the PWC so it was impossible to establish whether or not it actually worked.

    The third event that Mr. O’Brien refers to as part of his description of the “storm” is the effect of the introduction of the 2010 Arbitration Act, which, he says, made the situation even worse, due to the fact that the case-stated procedure in 1954 Arbitration Act that applied then was abolished and therefore no one could obtain judicial interpretation of the individual clauses in the PWC. Mr. O’Brien insinuates that this may be due to the drafters of this Act not giving full consideration to the use of the PWCs, where there was no authority to assist in the interpretation of the clauses therein. The 2010 Act effectively erased any chance that the construction industry had of creating a case precedent for the PWC.

    The final point that I would like to take from Mr. O’Brien’s article is his reference to the revisions to the PWCs, of which there were many and some of which had extremely problematic effects. He gave the example of the amendment in version 1.4 on 28th July 2011. An amendment therein stipulated that each party would pay their own costs in arbitration,regardless of which party effectively “wins”. This was enabled by Section 21 of the 2010

    Arbitration Act, with the removal of the prohibition on contract terms which makes parties liable for their own costs in any event. This amendment is considered to be hugely inappropriate and inequitable to be included in a form of contract drafted by the Government, particularly as it directly contrasts the Irish Superior Court rules where costs follow the event.

    Getting back to the main theme of my presentation, the dispute resolution mechanism under the PWC when it was first introduced was conciliation, followed by arbitration. With the introduction of the Construction Contracts Act, 2013, which came into force in July 2016, Statutory Adjudication became another step that had to be included in the PWC. Despite there being over fourteen changes made to the PWCs, no dispute avoidance mechanism was included alongside the dispute resolution mechanism. As such, dispute avoidance, which is part of the DAB procedure, was no longer in use in Ireland since the introduction of the PWCs in 2007.

    It was in 2015 that a third stage of the Luas Project, the Luas Cross City Project that was extending the Luas to the northern part of the City, commenced and had to use the PWC. The main Contractor in this stage of the Project was one of the five main Contractors in the second stage of the Luas Project and, although the Employer had changed its title, it was effectively the same Employer as in the first and second stages of the Project. Having been aware of the advantages of dispute avoidance that were implemented through the DAB procedure in both stages of this Project, they wished to have a similar procedure in their contract superimposed by the PWC. Having been the sole Standing DAB on the first and second stages of the Project, I was invited to participate in a discussion of how this might be done. This resulted in the creation of the position of the “Standing Conciliator”, and a set of rules had to be drafted for use in this position. The Project was substantially completed in November 2017 and, although it was a very complex Project with many difficulties, as it involved many civil engineering works in the middle of a busy city centre, all of the problems were resolved using the mechanism of the Standing Conciliator and without any reference to arbitration.

    Due to the success of the idea of the Standing Conciliator, the drafters of PWC picked up this idea and attempted to implement the principle of the Standing Conciliator in a “Project Board”, but, unfortunately, they failed to implement the essential parts of the rules that were developed for the Standing Conciliator under the third stage of the Luas Project. The main problem was that the dispute avoidance mechanism must begin from the very start of the events that lead to a dispute.

    SHOW SLIDE “MANIFESTATION OF A DISPUTE” AND EXPLAIN.

    In implementing the idea of the Standing Conciliator and the Project Board, the drafters of the PWC issued Guidance Notes to accompany the PWC. The present Guidance Note 3.1.1, Dispute Resolution, which, although expressing the correct sentiments of dispute avoidance, failed to show a proper procedure for achieving successful avoidance.

    SHOW GUIDANCE NOTES AND EXPLAIN WHERE THEY GO WRONG.

    I would like now to go to Clause 13 of the PWC and explain the problem with respect to the manifestation of a dispute in that Clause. In Sub-Clauses 13.1.1 and 13.1.2, it is stated that the dispute management procedure for resolution of disputes could only arise from Sub-Clauses 10.5.4 and 10.5.5 of the Contract. Therefore, dispute avoidance could only be used after the Employer’s Representative had given a determination and a dispute is in the making. Dispute avoidance is therefore too late. There are many other problems with Clause 13, but, unfortunately, I do not have the time to deal with those now.

    What about the future? What needs to be done now is to either properly adopt the mechanism of the Standing Conciliator; or else properly incorporate that mechanism into Contractual Adjudication. Of course, there is no problem in having Contractual Adjudication alongside Statutory Adjudication, but I will leave those ideas with Gerard Monaghan.

    On a final note, I believe that, at present, a firm of consultants, Indecon, has been appointed by the Office of Government Procurement to investigate the operation of the roles of the Standing Conciliator and the Project Board, with the view to updating national policy in dispute avoidance and I wish them luck with their work.

    I now hand you back over to Gerard.

    A paper presented to the Dispute Resolution Board Federation webinar 4th March 2021By NG Bunni Dispute Adjudication Boards were developed by FIDIC following the successful American experience of Dispute Review Boards and first appeared in the 1995 Orange Book for Design- Build and Turnkey projects. The Board’s function of “Review” was changed to “Adjudication” in…

  • Public Works Contracts Must Evolve

    Public Works Contracts Must Evolve

    Irish Public Works Contracts Must Evolve

    Resolving a disputed public works final account, with the assistance of a neutral third party, is as much a part of the construction process today as the physical setting out of the works. However, this is simply not the way it ought to be — and it’s high time it was fixed.

    We have an overwhelming obligation and responsibility to the generations to come not only as a nation, but as an EU member state, to address the reasons for such uncertainty in our public works contracts. This is particularly urgent if Ireland is to build and maintain her infrastructure into the future.

    The Perfect Storm

    June 8 2010 was the date that the Arbitration Act became law in this country. This occurrence was the last in a series of three unfortunate events that adversely affected the construction industry, which gave rise to what I respectfully refer to as the ‘Perfect Storm’. The two other events were the introduction of the new form of Public Works Contract (PWC) in

    2007 and the 2008 global financial crisis.  The perfect storm created by those events has continued to blow fiercely for more than a decade.

    Begin Again: the Introduction of the PWC

    Before identifying how we solve the problem, we need to understand it, and for that, we have to consider its origins.

    In 2007, the first versions of the PWC were introduced to replace the GDLA Blue & Yellow forms of contract (for use on Employer designed building works) and the IEI form of contract (for use on Employer designed civil engineering works). These new contract forms were developed as a reaction to a ‘politician’s brief’, and were purportedly to achieve out-turn cost certainty, as a disgruntled electorate were seemingly fed up with cost over- runs on government contracts.

    However, what many politicians didn’t understand (and indeed many mainstream journalists too) is that construction contracts are all about risk allocation and that, in order to achieve commercial value for taxpayers’ money, the risk ought to remain with the party who is best placed to manage it, and, critically, when you mismanage this allocation it can get quite complicated and quite expensive!

    In theory, the objective of the new PWCs was to procure tenders from Contractors that would become pure ‘fixed price lump sum’ contracts, thereby giving cost certainty. There would be no more undefined or provisional works in these new contracts nor would there be any contingency slush funds — contractors would simply be paid one pre-agreed price for one pre- defined package of work. Of course, it was expected that the lump sums tendered under the new regime would be slightly higher than those that would have been tendered under the previous government contract forms, but now, in theory, there would be no chance of any ‘runaway’ costs over that tendered lump sum.

    Consultant design engineers and architects did not escape the new regime either, as their brief was to comprehensively define and design the Works as required by the Employer’s brief, so that there would be little or no extras whatsoever. This is not an easy task to achieve, and perhaps that is why every international standard construction form of contract has a variation clause that does not vitiate the contract.

    Even projects for historical public building refurbishment works, which were traditionally tendered and contracted on a provisional basis with a schedule of rates, incorporated a new PWC ‘heritage strategy’ that required an investigative works contract to be carried out in advance. This was to uncover and record what lay beneath the rotting fabric of a building so that the architect could ‘comprehensively’ complete his or her design.

    This scope was then tendered and contracted on a fixed price lump-sum basis. That process, although looking good on paper, has in my experience not worked out too well either, and even the recent part refurbishment of Leinster House needed a ‘special iteration’ to the standard PWC which I’m sure helped bring that project in on time and on budget without risking any embarrassment of an out-turn cost overrun.

    Indeed, this new PWC ‘comprehensively defined and designed fixed price lump sum’ regime, sounded great in theory to those politicians and journalists who really didn’t understand the commercial mechanics of our construction industry. However, lurking beneath the v

    A Precedent for Problems

    The first element that contributed to the perfect storm was that these new PWC contracts had never been used in any jurisdiction anywhere in the world, and were simply unleashed upon the Irish public works sector completely unproven.

    At least the GDLA 1982 used as its foundation the RIAI 1980, which was itself based upon the terminology used in UK equivalent standard forms of building contracts, meaning that the Irish clauses, although not identical to the UK, shared a commonality of interpretation. The Irish IEI civil engineering form of contract was in fact almost identical to the UK ICE form, and shared commonality of clauses.

    But by far the most important aspects of the old Irish public works contracts was that both employers and contractors alike could rely upon the UK’s persuasive case precedent for the judicial interpretation of the contract clauses, thereby giving certainty to risk allocation to the parties under the contract.

    The issue with introducing an entirely new contract in the form of the 2007 PWCs, was that there was simply no precedent from which the parties could derive any interpretive certainty. Due to the compounding of problems that I address in this article, that unfortunate position remains to this day.

    Global Problems, Local Problems

    To compound matters even further, the 2008 global financial crisis became the second element in the making of this perfect storm, in which the Irish construction industry effectively collapsed just as its infant new Public Works Contracts were being put to use.

    During those bleak years of recession, many contractors tried their very best to stay afloat, some going abroad to work in different jurisdictions. Others stayed home and picked up whatever scraps they could on public maintenance works under the new PWC forms.

    During this period, the tendered lump sums on the PWCs did not increase as they ought to have done. This was mostly due to the recession, but also partly because many contractors tendered lump sums still unsure of the ramifications resulting from the new powers, duties, and responsibilities being allocated to each party under the new forms.

    Contractors were not alone in this regard, ER’s and employers were also unsure of the workings of the new PWCs and there was a sense of “keep the heads down and keep working”, and any skirmishes (for example over a 10.3 or the application of a T1 or T2 threshold contingency) never really went anywhere. In the early days of the recession, nobody really went to dispute.

    In fact, one might be forgiven for believing that after the first five years, the new PWCs were a success and working just fine.

    Effectively, the 2008 crisis resulted in the stunting of any productive assessment of how the PWC performed in practice and whether it actually worked or not. This was because no one had really used it or tested it.  We were all just simply trying to survive, and contracts don’t mean a whole lot in those circumstances.

    Interpretive Dance

    Under the new PWC1, disputes were to be resolved ‘in the usual way’, by step-down conciliation, and then if not resolved, to be finally determined in domestic arbitration under the Arbitration Act 1954.

    The 1954 Act had a case-stated procedure under Section 35, which was a useful tool at the disposal of an Arbitrator who could, if he decided that there was insufficient legal authority available on an issue at large during a reference, seek leave of the High Court to have the High Court to answer a legal question or questions on the matter.

    One would have thought that this case-stated procedure contained in the 1954 Act would have been very useful indeed for building up a library of judicial interpretation of the individual clauses in the PWCs, but alas that wasn’t to be.

    On the June 8, 2010, the new Arbitration Act came into force in Ireland, abolishing the case-stated procedure.

    This was the third element, the perfect storm was now complete and the new PWC ship had no rudder, and no harbour in sight.

    The decision to abolish the case stated procedure in the 2010 Arbitration Act may have been made with the intention of strengthening the protection of arbitral tribunal decisions from court interference, in order to make Ireland a more attractive neutral country as the seat of international arbitrations. 

    But the drafters of the 2010 Act perhaps did not appreciate that the country’s construction industry had only three years previously been encumbered with a brand new suite of public works contracts, where there was no authority whatsoever to assist in the interpretation of the clauses therein. So, in 2010, not only was there no persuasive case precedent from other jurisdictions available to assist in PWC clause interpretation, but the only portal to create our own case precedent had just been sealed shut by the 2010 Act!

    It has remained that way now, for over a decade.

    Increase in Works, Increase in Disputes

    As the economy began to recover from the 2008 crash, the volume of public works began to increase again, and with that the volume of disputes. Interim determinations by Employers’ Representatives gave rise to disputes, and disputes became more frequent as users each formed a view on how the various PWC clauses and schedules could be interpreted.

    There is no formal public record, redacted or otherwise, which logs the outcome of what must be, at this stage, hundreds if not thousands of disputes between public sector employers and contractors over the past decade.

    What our industry does have, is a trail of revisions to the various PWCs where one might suspect, that the outcome of some of these confidential disputes have warranted a unilateral change here or an edit there. Indeed, taken together, these amendments to the PWCs do form a sort of precedent, albeit not a very judicial nor indeed an objective one.

    Inequitable Revisions

    One such unilateral revision was slipped into the Tender & Schedule in FTS v1.4 on the 28 July 2011.  It is one which effectively stipulates that each party pays their own costs in arbitration, even if they win, and even if the Contractor beats an Employer’s sealed or Calderbank offer, he still  pays  his  own  costs!  Such  a  provision became  possible  when  Section  21  of  the

    Arbitration Act 2010 removed the prohibition on contract terms making parties liable for their own costs in any event. The idea behind this removal

    is  understood  to  have  been  to  facilitate  US parties to arbitrate their disputes in Ireland, but the effect on Irish disputants seems to have been missed in the process.

    This is widely considered to be a highly inappropriate and inequitable term to be included in a government drafted public works contract. Furthermore, it is a term which contrasts starkly with the rules of the Irish Superior  Courts  where  ‘costs  following  the event’, which is also the default position in most other common law systems.

    This grossly unfair provision has been unilaterally forced upon all public works contractors, who now have no way of recovering their legal and expert costs even when they succeed in defeating a public employer in arbitration.

    Because of this grossly unfair term, many contractors simply cannot afford to take a risk, of getting a favourable award in arbitration, as their legal and expert costs will be offset against his recovery and will most likely dilute if not drown out the quantum of the substantive award.

    This provision also completely destroys the Calderbank sealed offer procedure that is crucial to trigger parties into properly assessing and reassessing their risk exposure to costs and settlement expectation during the Arbitration referral.

    The most experienced practitioners will be only too aware that many arbitrations do not go all the way to final award, but rather are settled in a parallel confidential mediation process because a party’s live risk profile changes during the pleading, discovery and plenary processes of arbitration.

    As is well understood, the award of, and liability for costs, are an intrinsic part of the dispute resolution process in construction. That crucial element was unilaterally stripped away, making arbitration somewhat of an impotent procedure from the contractor’s perspective.

    Ireland as a member state in the EU, and of the common  market  for  EU  tendering  of  public works projects above €5m, cannot allow inappropriate and inequitable provisions remain in its Public Works Contracts that effectively deprive public works contractors access to due process.

    Where are we now?

    This paper opened with the words:

    Resolving a disputed public works final account with the assistance of a third party neutral is now as much a part of the construction process today as the physical setting out of the Works. However, this is simply not the way it ought to be, and it’s high time that it is fixed.

    What I have found, is that public employers and their representatives make interpretations and determinations on PWC 10.3 claims based upon a ‘rehearsed party line’ of what a particular clause was intended to mean by the drafters, rather than forming an independent and objective view themselves of what it actually means.

    Often, a weaker or less learned participant of a PWC does not consider the merits of how a clause or provision may have (or could have) been interpreted at the time of tender. One often surmises that the participant is perhaps following a circular of orders that instructs the only internal interpretation allowable. This is often what triggers a contractual dispute on the PWCs, which is then referred to a third party neutral for assistance.

    In my experience, this is where the entire process starts to heave under its own dead weight.

    The responsibility of a third party neutral to a dispute cannot be understated and is of paramount importance to the entire construction industry.  There  are  exceptional  practitioners who fully understand this responsibility and can provide that highly valued neutrality and objectivity with competence and conviction — traits that are particularly required by conciliators, adjudicators, mediators and arbitrators alike.

    Unfortunately, there are Contractors, Employers, Lawyers, Public Servants & Construction professionals that have been drawn to the field of ADR as third party neutrals, but they suffer from an unconscious bias, never fully shaking off their previous careers and, without the benefit of judicial case precedent direction, they are being retained and appointed because of their own consistent and unchanging interpretations of the PWCs.

    This is simply not acceptable anymore and after a decade of PWC uncertainty, we as an industry, have a responsibility to fix this problem now.

    So What is the Solution?

    1.   Amend the Arbitration Act 2010 and reinstate the case stated procedure. That way we can build up a case precedent of judicial interpretation of PWC clauses the way that it ought to be in a common law jurisdiction like Ireland. This will provide certainty and also assist the third party neutral in making robust decisions.

    2.   Remove the term in the PWCs that parties pay their own costs in arbitration and revert to costs following the event, as per the rules of the superior courts. Also, remove the amendments that adversely affect the traditional Calderbank procedure.

    3 February 2021


    1 Long before the option to refer a construction payment dispute to statutory adjudication under the Construction Act 2013

    Irish Public Works Contracts Must Evolve Resolving a disputed public works final account, with the assistance of a neutral third party, is as much a part of the construction process today as the physical setting out of the works. However, this is simply not the way it ought to be — and it’s high time…

  • Covid-19: Ex Gratia Payments and Public Works Contracts

    Covid-19: Ex Gratia Payments and Public Works Contracts

    You may recall my comments in May last year when the OGP first published guidance in relation to Employers making ex gratia payments to Contractors for costs associated with the stoppage of works and closure of sites. I both started and finished with the line:

    Private contractors on public works contracts do not get gifts or favours from the government.

    Having considered the OGP’s latest publications on the ‘Covid Co-operation Framework’, which proposes ex gratia payments for the costs of implementing measures on construction sites required under the ‘Return to Work Safely Protocol’, the sentiment in that line still remains valid.

    The Current Position

    First, let’s take stock of the current position: there are now two ex gratia relief mechanisms offered on a ‘without prejudice’ basis to contractors who entered into Public Works Contracts before the occurrence of Covid-19.

    The first of these provides a contribution from the Employer to the Contractor for their costs of demobilisation, securing the site and prolongation costs, where these result directly from the stoppage of non-essential works and closure of sites due to Covid-19.

    The second ex gratia relief provides a contribution from the Employer to the Contractor for: (1) the costs of re-mobilising and getting back to work after the Covid-19 suspension, and (2) the costs for carrying out the remaining contract works under heavily disrupted [socially distanced] conditions, collectively labelled “the Return to Work Safely Protocol” (the ‘Protocol’).

    Construction site

    First Ex Gratia Payment Relief

    In my opinion, the stoppage of works and closure of sites in respect of non-essential works results in a suspension to the works that Employers’ were obliged to instruct in compliance with directions from Government. Do not forget, the direction from the office of the Taoiseach at the time was that Employers were to decide whether or not works were ‘essential’ and to inform Contractors of this.

    It follows, if Employers decided that works were non-essential and communicated this to Contractors as they should have, this amounts to a de facto instruction to suspend the works. That instruction then falls squarely within Event 3 Part K of the Tender and Schedule entitling the Contractor to time and money. Event 3 reads as follows:

    “The Employer’s Representative directs the Contractor to Suspend the works under sub-clause 9.2.”

    The OGP has sought to avoid this issue and has instead suggested that the closure of sites and stoppage of works was an Event 15 under Part K of the Tender and Schedule entitling the Contractor to time only.

    Event 15 reads as follows:

    “Delay to the Works caused by the order or other act of a court or other public authority exercising authority under Law.”

    I do not agree with the OGP’s position that the closure of sites and stoppage of works qualified as an Event 15. This is for a number of reasons:

    • First, as set out above, as a matter of fact, in compliance with directions from government, it was for Employers to decide whether or not works were essential and to inform Contractors. Where this process was not followed in respect of non-essential works, it is simply Employers seeking to shirk responsibility and avoid having to give both time and money pursuant to Event 3.

    Unfortunately, the OGP’s stated position gives misplaced credibility to Employers that did not follow the process that was envisaged by the Department of the Taoiseach.

    • Second, the OGP’s logic that the suspension falls within Event 15 at all, is incorrect. This is because, plainly, it was not “the introduction of a law or the order or act of a court or other public authority” that “caused” the delay to the works – what actually caused delay to the works was the occurrence of a global pandemic and the subsequent outbreak of the illness in Ireland.

    The pandemic itself is the root cause of the delay, not any law or order brought about as a result of it. The introduction of laws or orders made to deal with the pandemic are a secondary matter, which the OGP is seeking to rely upon in order to shoehorn site closures and stoppages of works into Event 15.

    • Third, and following on directly from my second point, in any event the Regulations made by the Minister for Health which underpinned the Taoiseach’s announcement with regard to the closure of sites were not introduced until after sites were closed and until after the instruction by the Employer with regard to suspension of the works should have been given.

    The OGP cannot therefore properly rely on the making of those regulations as a basis for shoehorning the suspension into Event 15, since the Regulations only came into effect after suspension occurred.

    Public sector Employers’ and the OGP’s approach in relation to this matter can be seen as even more cynical when viewed from the perspective of the indemnity provided by the Employer to the Contractor pursuant to sub-clause 3.5(1) of the Contract.

    That indemnity is for “liability for death, injury, or illness of any person or loss of or damage to any physical property that the Contractor incurs in the course of performing the Contract to the extent caused by the negligence of the Employer”.

    Considering the breath of this indemnity, which obviously encompasses issues that might arise as a result of Covid-19, the Employer should have taken immediate and appropriate action to instruct the suspension the works.

    Unfortunately, this is not what occurred in practice, with many Employers leaving it to the Contractor or the Employer’s Representative to take action independently, notwithstanding a direction from Government that it was for the Employer to take such action.

    Second Ex Gratia Payment Relief

    The second ex gratia relief relates to costs incurred by Contractors in implementing measures on construction sites to comply with the Return to Work Safely Protocol.

    This time, the OGP has decided that compliance with the Protocol is now not even an Event 15. Its position has hardened and it now states that the Contractor is neither entitled to time nor money in completing its works in compliance with the Protocol:

    “The OGP considers that the standard forms of Public Works Contracts (PWC) do not provide an entitlement to Contractors to an extension of time or to recover any costs that may arise as a result of the introduction of the Protocol and/or the implementation of the Protocol Measures.”

    I do not agree with the OGP’s stated position that the implementation of the measures to comply with the Protocol on construction sites does not give rise to any entitlement under the Contract.

    My view is that the compliance with the Protocol is, at its most basic, an additional constraint on the works that gives rise to an Event 1 under Part K of the Tender and Schedule (a Change Order) which entitles the Contractor to both time and money.

    Notwithstanding its stated position, the OGP also notes that the ex gratia payments agreed under the proposed framework for dealing with the implementation of measures pursuant to the Protocol are to help to “ease the financial burden on Contractors”. This is, again, a cynical statement, given that any ex gratia payments will be limited to a maximum of 50% of the Contractor’s actual costs, but ‘only’ on the basis that the Employer’s budget allows it to pay out even that.

    Consequently, the absolute best that Contractors can even hope to obtain is 50% of their costs, but will likely get far less with Employer’s seeking to rely on restricted budgets as the reason for not being in a position to pay out.

    OGP Overall Strategy

    The ex gratia payment reliefs, taken together, are no more than the OGP seeking to support Public Sector Employers in attempting to get a better deal by agreeing to make payments to Contractors at a lower level than those to which Contractors’ are actually entitled.

    It is the difference is between charity and entitlement, and prudent Contractors should seek to exercise their entitlement if as good as, or a better deal, is not on the table under the ex gratia payment procedures.

    Furthermore, Contractors need to bear in mind the additional barbs included in the ex gratia payment mechanisms, which would make it unattractive to bring claims after agreeing to take ex gratia payments – these include the Employer obtaining “open-book” access to Contractor’s costs and records, and the ability to claw back any ex gratia payments made should the Contractor be successful in a claim.

    The OGP’s ex gratia relief and payments are, on the one hand, a proactive initiative to restart works and get back to work safely, whilst on the other, an initiative to reduce the Government’s potential exposure, by creating the ‘lesser of two evils’ option, inducing Contractors into agreeing ‘settlement payments’ in exchange for a waiver by the Employer to imposing Liquidated Damages for delay.

    This OGP initiative may suit some Contractors who have substantially weathered the storm, with the assistance of the Covid-19 weekly wage subsidy to their staff, and now simply want to get back to work, but to other contractors these ex gratia relief charitable offers will simply not be enough to cover the shortfall and losses. As a result, they will have no choice but to pursue their full compensation entitlement.

    6 August 2020

    You may recall my comments in May last year when the OGP first published guidance in relation to Employers making ex gratia payments to Contractors for costs associated with the stoppage of works and closure of sites. I both started and finished with the line: Private contractors on public works contracts do not get gifts or favours from the government.…

  • Covid-19: Public Works Contracts and ‘Ex Gratia’ Payments

    Covid-19: Public Works Contracts and ‘Ex Gratia’ Payments

    PRIVATE CONTRACTORS on public works contracts do not get gifts or favours from the government. For this reason, the publishing by the Office of Government Procurement (OGP) of a draft letter of agreement dealing with ‘ex gratia’ payments from Employers to Contractors can only be cautiously welcomed.

    For reasons that I am sure you are well aware of, which include, inter alia, the indemnity provided by employers for negligence causing illness or death under Clause 3.5, this action by the OGP is not unexpected. However, you can be sure that these ‘ex gratia’ payments will not cover the full extent of employers liability to contractors now, or for the many months to come long after 4th May 2020 when the country, slowly and progressively, gets back to work — which will certainly not be under the same conditions that the work was tendered or contracted upon.

    As a general point, I am minded to conclude that this move by the government, to offer any ex gratia payment, is the genesis of setting an acknowledgement (or dare I say) precedent in paying compensation to contractors of their actual prolongation losses, which is in contrast to the normal denial under the controversial tendered schedule 2D daily delay rate.

    Contracts page: Contract document with magnifying glass

    With regard to the specifics of the OGP’s ‘Model Form Supplemental Agreement’, entitled ‘Public Works  Contracts Covid-19 EX-GRATIA PAYMENT BY THE EMPLOYER LETTER AGREEMENT v1.0’ published on April 23, I comment as follows:

    Entitlement to Delay Costs

    I disagree with the employer’s assertion at Paragraph 4 that the contract does not provide an entitlement for the contractor to recover costs associated with the delay arising from the closure of the site in the circumstances  contemplated  by  the  Public  Health Measures.

    If the employer was correct in his assertion in this regard, then the employer’s position would simply be that the Covid-19 pandemic is a Part 1 Schedule K Event 15, and would give time but no money. Hence, any payment would be a genuine ex gratia gift.

    There exists a very important aspect that does not make this pandemic a Part 1 Schedule K Event 15 — which carries a Yes/No designation to delay and compensation — and  this  is  that  the  Office  of  the Taoiseach  decided  that  each  employer  (public  and private) had to decide for themselves, [not the government nor not by any act or law] whether their site or project was essential or non-essential and whether to remain open or not1.

    Therefore, if the site was to remain open, then it could only do so under the disruption of social distancing constraints, (which could not be denied by the employer under the risk of the indemnity given under clause 3.5), and a change in the manner of how works are to be executed and a requisite EoT would apply by way of change order Part 1 Schedule K Event 1, which carries a Yes/Yes designation to delay and compensation.

    Or, if the site was to be closed, then the works could only be suspended under Part 1 Schedule K Event 3, which carries a Yes/Yes designation to delay and compensation.

    That being so, this ex gratia payment is a welcome gift but will be offset against the actual costs that contractors will seek to claim, and should claim.

    Opening the Kimono

    Paragraph 3(a) (i) & (ii) needs to be, and will be, approached with extreme caution by contractors.

    For the purposes of the employer, or the party nominated on its behalf, determining the amount of ex gratia payment the contractor has to:

    (i)  provide a complete and full breakdown of the contract preliminaries on a transparent and “open book” basis; and [represent and warrants that]

    (ii)  it has made all its records, supporting and vouching material available”

    Whilst a claim for prolongation loss and expense, is generally the remedy for critical delay caused by an employer culpable event under a standard form, to put the contractor back into the financial position it was in before the event or breach occurred, even in arbitration, disclosure or discovery is not carried out on an “open book” basis to prove such loss. Supervised inspection, of agreed categories of discovery, or relevant categories directed by an arbitrator is the norm, but not an open-ended free for all for opposing parties to indulge.

    “Open book” is a completely undefined term in the supplemental agreement letter, and if signed by a contractor, then the definition would come down to whatever the employer required in order to satisfy its curiosity.

    “All its records” is another completely undefined term in the supplemental agreement letter, and if signed by a contractor, could expose it to the whims of overeager ER.

    Furthermore, the OGP Update 1 dated 14 April 2020, Section 4 “Calculating Ex-gratia Payments” sets down a completely obscure formula that in no way produces a figure, which would compensate the contractor for its actual losses as a result of Covid-19.

    Unacknowledged Future Costs

    At Paragraph 3 (c) the employer seeks to limit his exposure to liability with regard to the denying of any ex gratia claim / payment for supervisors (individuals) who have left employment in connection with the works, or have been laid off since 28 March 2020. While this might be the employer’s prerogative to do so, as he is the one issuing a “gift”, the cost of a supervisor or any individual that had to be laid off or made redundant; and

    the consequential costs of re-employing individuals — which may include an increase from a price fluctuation in wages — may very well form part of the substantive claim for compensation which the contractor will be entitled.

    Payments are ‘Final and Binding’

    Paragraph 4 states that the decisions of the employer, relating to the ex gratia payment “including the amount and make-up of it are final and binding”.  Is final and binding forever? Or just until, for example, the employer decides he has paid too much ex gratia under paragraph 7?

    To me, this seems to be a moot point since any sums that contractors do not recover through the ex gratia payment will likely form part of a claim under the contract. The nature of the ex gratia payment being final and binding is therefore partially irrelevant.

    Site Closure Costs

    At Paragraph 6, the employer expressly distances itself from any liability or responsibility in respect of “Site Closure Costs”. These costs and their relationship with the contract are kept deliberately vague. In particular, the relationship between site closure costs and  compensation  under  a  suspension  pursuant  to Part One schedule K Event 3 is entirely avoided. This is a glaring absence.

    By the contractor signing up to the supplemental letter (purportedly extending the entire agreement) is he now essentially accepting that the ex gratia payment (gift) is in fact the site closure costs? When in fact, they most certainly cannot be — especially in the manner in which the employer calculates the ex gratia payments, under Section 4 of the OGP Update 1 dated 14 April 2020.

    Claims, Maintaining Entitlements and Clawbacks

    Paragraph 7 states: “If the contractor makes any claim under the contract or otherwise against the employer in connection with the Public Health Measures or the Regulations, and is successful in such claim, the amount payable to the contractor as a consequence of such claim shall be reduced by the amount of the ex gratia payment.”

    This clause is interesting in that it specifically acknowledges the ability of contractors to make additional claims for money on top of whatever is agreed as an ‘ex gratia’ payment. In order that contractors maintain their entitlements so that they can pursue such claims, I would advise all contractors to raise 10.3 notices now in respect of their actual costs, and or notify the ongoing costs, to protect themselves from any attempt at an employer time bar further down the road.

    ‘Public Health Measures’, while published by gov.ie, do not change the fact that the Covid-19 pandemic has not been classified nor does it meet the criteria of a part One Schedule K Event 15, and it is for the employer — the government — under a public works contract, to either suspend the works under an Event 3, or to instruct continuance at social distancing and or other imposed constraints on the manner in which the works are executed under Event 1 — both circumstances entitling the contractor time and compensation.

    I see a potential sting in the scorpion’s tail of the supplemental agreement (letter) in the second part of Paragraph 7, which states:

    “And in the event the ex gratia payment exceeds the amount determined is due to the contractor in connection with such claim, the contractor shall pay to the employer the amount of such excess within 10 days of such amount being demanded.”

    If the employer determines, wrongly in my view, that any such other claim in connection with the public health measures, that the Schedule 2D where a contractor has tendered a €zero daily rate applies, will the contractor then have to give the entire ex gratia payment back to the employer?

    Private contractors on public works contracts do not get gifts or favours from the government.    

    28 April 2020


    1 Also, Section 3 of the OGP Update 1 dated 14 April 2020 so stipulates

    PRIVATE CONTRACTORS on public works contracts do not get gifts or favours from the government. For this reason, the publishing by the Office of Government Procurement (OGP) of a draft letter of agreement dealing with ‘ex gratia’ payments from Employers to Contractors can only be cautiously welcomed. For reasons that I am sure you are…

  • Covid-19: Key Issues for Contractors under Public Works Contracts

    Covid-19: Key Issues for Contractors under Public Works Contracts

    NO ONE KNOWS WHAT the full impact of COVID-19 will be on the economy or wider society in Ireland. However, what we do know is that its impacts will be wide-ranging for every industry, including construction.

    As yet, there has been no direct instruction from government that construction sites be closed.

    The position, on the basis of the Taoiseach’s address of 24 March 2020, is that where social distancing measures can be adequately implemented, then sites may stay open. This is positive for the industry and the economy overall, but with the inevitable delays that will result to projects due to the wider impacts of COVID-19, Contractors must be conscious of their exposure.

    workers on construction site

    Contractors operating under the Public Works Contract may feel particularly concerned considering the risk profile of that contract and the onerous provisions with regard to entitlements to time and money. In particular, Contractors need to be mindful of the provisions to be complied with in order to obtain or maintain entitlements.

    With that concern in mind, we set out below some critical matters for Contractors engaged under the Public Works Contract to consider in the context of the COVID-19 crisis.

    Communications with the Employer

    As an initial and overall point, the most important thing to do now is to maintain the relationship, communicate and, if possible, agree steps to take with the Employer — now is the time to pick up the phone and to discuss matters sensibly. That said, notwithstanding any discussions that do take place, Contractors must at all times comply with the contractual provisions to ensure no entitlements are lost.

    The guidance to Employers issued by government does appear to be to take a cooperative and conciliatory approach to dealing with the issues thrown up by COVID-19. In particular, in a guidance note to Employers issued through the Construction Procurement Reform website, who operate under the remit of the Department of Public Expenditure and Reform, Employers are directed towards clause 4.1 of the Public Works Contract, which provides that the Employer and the Contractor shall co-operate. The guidance reads as follows:

    …sub-clause 4.1 Co-operation should be used as the vehicle to assess the likely impact of the Covid-19 response measures on the progress of the works, the issues currently arising and any potential mitigating measures that can be taken. Where the issues arising are linked to the impact of Covid-19 response measures the Contracting Authority [Employer] should adopt a proactive and collaborative approach to address the issues.”

    As a Contractor, if you are faced by an Employer/Employer’s Representative that is unwilling to engage or does not engage of their own volition pursuant to clause 4.1, some pointed correspondence quoting the above guidance may assist in generating the required engagement.

    Extensions of Time and Adjustments to the Contract Sum

    Delays
    It is unavoidable, delays will occur as a result of the COVID-19 crisis. Whether it be social distancing measures slowing down work progress, or delays in the wider supply chain causing materials to take longer to come to site, progress will be curtailed and deadlines missed.

    In order to maintain entitlements, Contractors must operate within the contractual conditions and notify the delay pursuant to clause 9.3 or 10.3 of the contract. Remember, under clause 9.3 Contractors are required to issue a notice when they become aware that work under the contract is being or is likely to be delayed.

    Contractors are aware that work is likely to be delayed as of now, so the relevant notice should be submitted. Contractors must also input the required follow-up notices to maintain entitlements pursuant to clauses 9.3/10.3.

    In the context of COVID-19, the Contractor should also consider its position under clause 2.5 Safety, Health and Welfare at Work Act 2005 and Safety, Health and Welfare at Work (Construction) Regulations 2013 which provides:

    “2.5.1 The Contractor shall [without limiting other obligations] ensure, so far as is reasonably practicable, that the Works are constructed to be safe and without risk to health…..” [a worrying choice of words in this context perhaps?]

    but one of his other obligations with regard to proceeding diligently [without delay] under Clause 9.1.3 is that:

    “9.1.3 …The Contractor shall, unless the Employer’s Representative directs otherwise, proceed regularly and diligently in order to achieve Substantial Completion of the Works and each Section by its Date for Substantial Completion. “

    Without exercising social distancing, the constructing of the works will [according to the current guidance from the Department of Health] create a risk to health.

    It appears to be reasonably practicable to exercise social distancing on many sites, but in doing so it will also effect efficiency of output, and slow down overall progress. This will most certainly put the contract Date for Substantial Completion of the Works in jeopardy [and thus heighten the risk of liquidated damages being levied against the Contractor] unless the ER grants an appropriate extension of time.

    Is the ER obligated now to direct otherwise and instruct social distancing on sites as a Change Order and limit the Contractors other obligations referred to in clause 2.5?

    The statement issued on the Construction Procurement Reform website recommends to Employers that they should utilise the clause 10.4 mechanism in relation to potential issues faced as a result of COVID-19. Clause 10.4 permits the Employer to request a proposal from the Contractor with regard to an instruction to be given by the Employer. The guidance states:

    …it is suggested that the ER make use of sub-clause 10.4 Proposed Instruction by requesting the Contractor for a proposal to address the particular issues as they are identified under sub-clause 9.3.”

    Our advice to Contractors is make proposals under 10.4 for a Change Order on the basis of additional constraints being imposed on completing the works causing delay, those constraints being the recommendations of the Department of Health with regard to social distancing. This Change Order will result in both an extension of time and an adjustment to the Contract Sum pursuant to Event 1 in Part 1 K of the Tender and Schedule.

    It is also specifically noted in the guidance on the Construction Procurement Reform website that many items of delay may be dealt with pursuant to Event 15 in Part 1, K of the Tender and Schedule. This event is a delay event but not a compensation event, so provides an extension of time, but no adjustment to the Contract Sum. It seems likely that Event 15 will be the official default position on all government contracts for COVID-19 giving Contractors’ time, but no money.

    Event 15 reads as follows:

    Delay to the Works caused by the order or other act of a court or other public authority exercising authority under Law, that did not arise as a result of or in connection with an act, omission or breach of Legal Requirements of the Contractor or the Contractor’s Personnel or a breach of the Contract by the Contractor.

    There is currently a potential difficulty with regard to how Event 15 occurs as that there is no ‘Law’ (as yet) on which to hang an entitlement for an extension of time. All actions that are being taken stem only from ‘guidance’ as issued by the Department of Health. This leaves it open to Employers, if they wished to do so, to be difficult with regard to granting and extension of time under the contract pursuant to Event 15. This is obviously subject to change on the basis of emergency legislation due to be passed.

    That said, should there be difficultly in bringing the Employer to the table to have sensible discussions in relation to how matters should be dealt with in respect of the continuation of the works, it may be useful to remind the Employer of the indemnity he has provided to the Contractor pursuant to clause 3.5 of the contract. Clause 3.5 reads as follows:

    3.5 Employer’s Indemnity
    The Employer shall indemnify the Contractor against:
    (1) liability for death, injury, or illness of any person or loss of or damage to any physical property that the Contractor incurs in the course of performing the Contract to the extent caused by the negligence of the Employer and
    (2) liability for property damage that is the unavoidable result of executing the Works in accordance with the Works Requirements

    Conceivably, on foot of clause 3.5, should the Employer be negligent with regard to how he conducts himself in relation to the COVID-19 crisis and should such negligence result in death or illness of any person due to COVID-19, then the Contractor will be indemnified in respect of such negligence.

    Therefore, the Employer has a significant interest in coming to the table to discuss, agree and instruct sensible and achievable actions to deal with COVID-19.

    Suspension
    Should it not be possible to implement social distancing measures as a result of the type of works that are being undertaken on a particular project, the Employer may decide to suspend the works, or, if a proposal is sought from a Contractor pursuant to clause 10.4, the Contractor may decide to propose that the works be suspended.

    Such suspension would qualify as both a delay and compensation event pursuant to Event 3 in Part 1, K of the Tender and Schedule. As a result, the Contractor would benefit from both an extension of time and an adjustment to the Contract Sum.

    There is also a question of potential negligence here, should the Employer fail to instruct suspension of the works either of his own volition or on foot of a proposal from the Contractor pursuant to clause 10.4, particularly should an operative on site have tested positive for COVID-19. Such issues seem yet to have arisen, but surely this will inevitably occur.

    Conclusion

    The COVID-19 crisis is fertile ground for claims-orientated Contractors and obstructive Employers to lose site of the public health emergency and embroil themselves in wasted exercises of attempting to make or save money under Public Works Contracts. It is hoped that perspective will win out and that all Contractors and Employers take a different approach.

    What needs to occur is for Employers and Contractors to sit down together to identify the best way forward and for both to work together to ensure that, where possible, work progresses in manner that is conducive to maintaining public health and facilitates the carrying on of as many construction projects as possible. Until these conversations happen and decisions are taken on foot of those discussions, Contractors should be mindful to maintain their entitlements in accordance with the contractual provisions. As delays do occur, extensions of time and adjustments to the Contract Sum, where appropriate, should be given in a proportionate manner and be reflective of what is happening on the ground.

    Construction is vital to economic activity and if activity can continue in a safe manner, it should. Moreover, the industry has a responsibility to the wider economy to keep activity going, assuming it can do so.

    • John FFF O’Brien is principal of John Farage O’Brien, specialists in resolving construction disputes and providing expert support if the legal route is taken

    25 March 2020

    Contact to action: info@johnfarageobrien.ie

    NO ONE KNOWS WHAT the full impact of COVID-19 will be on the economy or wider society in Ireland. However, what we do know is that its impacts will be wide-ranging for every industry, including construction. As yet, there has been no direct instruction from government that construction sites be closed. The position, on the basis…

  • Top Public Sector Award six years running

    Top Public Sector Award six years running

    Greystones businessman John O’Brien’s company has won the highest award from Public Sector magazine for 2024, and for every year since 2017.

    O’Brien’s company, John Farage O’Brien Ltd, which operates from offices on Delgany’s Priory Road, has just been presented with the 2024 Legal Dispute Resolution Award by Public Sector magazine in its annual Excellence in Business Awards.

    John was so taken aback by the phone call to tell him his firm had won again, “I couldn’t believe it,” he said. “I told them they had given me the same award last year, and they said ‘we know, and we are giving it to you again this year’.”

    The prestigious award comes in recognition of the firm’s work in advising and representing those involved in construction disputes, many involving the public sector, and its founder’s role as a mediator, conciliator and arbitrator in successfully resolving disputes which often involve tens or even hundreds of millions of euro in contract value.

    O’Brien said: “It is incredible, to win this award for the second year running. It’s unbelievable news for our team. But in reality, they deserve this recognition for the work they do — and for the contribution it makes to business involving the public sector.

    The Legal Dispute Resolution Award

    “The public sector is a huge employer of construction firms, civil engineering companies, surveyors and many other construction professionals, operating many contracts, and when disagreements turn into disputes we are always on hand to help resolve them.

    “We have been involved in cases worth over €2.5 billion in contract value since 2003, with amounts in dispute running from a few hundred thousand up to tens of millions. The vast bulk of these are resolved without resorting to adversarial and public litigation in court, saving huge sums in legal fees, huge stress for the parties involved, and huge amounts of public money.

    “Between us, we marshall all of the very wide range of skills that are needed in this complex area. We have helped resolve innumerable disputes, and I am very pleased that my team and I have had that contribution recognised by being chosen for this prestigious award.”

    The firm was founded by the well-known Greystones resident in 2003. It specialises in resolving disputes in the construction sector, representing clients at all forms of alternative dispute resolution. O’Brien himself is a fully qualified and accredited mediator and arbitrator, where he serves as the ‘referee’ in disputes over the terms of construction contracts and brings to the role a lifetime of experience in the construction sector and 15 years of work resolving disputes.

    John Farage O’Brien also provides support services to legal teams which represent clients in open court or private arbitration tribunals, where their efforts at mediation or conciliation have broken down.

    Alternative dispute resolution includes methods of resolving disputes that do not involve court action, which can be difficult and costly. Instead, processes such as arbitration, adjudication, conciliation, and mediation are used to resolve conflicts, once the parties in dispute agree to use them.

    O’Brien has long experience as a project manager on major civil engineering, railway infrastructure and building projects in Ireland and Britain and has honed his skills in the the dispute resolution arena since 2003, with extensive experience as a dispute manager, an advocate, a conciliator and as a practising arbitrator and mediator.

    Greystones businessman John O’Brien’s company has won the highest award from Public Sector magazine for 2024, and for every year since 2017. O’Brien’s company, John Farage O’Brien Ltd, which operates from offices on Delgany’s Priory Road, has just been presented with the 2024 Legal Dispute Resolution Award by Public Sector magazine in its annual Excellence in Business…

  • The view from the arbitrator’s chair

    The view from the arbitrator’s chair

    The View From the Arbitrator’s Chair

    John O’Brien has a fundamental belief that in life people can generally be separated into two distinct groups, those with integrity and those without. He has found that this aspect has given rise to many of the disputes his firm has been involved in over the years

    Photo by Roger Kenny. www.rogerkenny.ie

    JOHN’S VIEW IS that a significant number of sub-contractors — and indeed main contractors — have carried on their business for many years with an unhealthy reliance on trust rather than on contract. In times of continuity of work or in a construction industry boom, arrangements based on trust and past history have worked reasonably well where symbiotic working relationships take precedent over dispute. About us

    The Irish construction industry crash and subsequent recession brought in its wake a rash of disputes where parties pulled back to the respective contractual positions they initially signed up to, or to a contractual arrangement they understood at the time of contract. While we found there were genuine disputes on entitlement, we also found that there were also many ‘fuzzy’ disputes created by parties to survive the downturn.

    Artificial disputes are manufactured simply to avoid payment in an attempt to maximise profits

    Says John O’Brien: “We have seen an increasing number what I call ‘artificial’ disputes, where one party simply owes money to another under contract, but has not got the requisite funds to meet the contractual obligation to pay, as that party is itself owed money or simply cannot sell the asset(s).

    “If this party admits that he has not got the money to meet his liabilities, then his company may be forced into receivership or liquidation and any chance of recovery is to a great extent lost. The party who owes the money simply ‘invents’ a dispute to buy his company valuable time. He then procrastinates through the negotiation and conciliation processes in the hopes that his own financial position improves to a point where he can meet his liabilities.”

    Other artificial disputes are manufactured simply to avoid payment in full, in an attempt to maximise profits.

    Main contractors identify two sources of revenue on construction contracts. The first and obvious source is the employer which has contracted them, and the second source — at least where the main contractor has little regard for future relationships — is made up of contractually naive sub-contractors. Advantage is often taken.

    John notes that the clue to the term “implied professional skill” lies in the title “contractor”. About us

    If you are a contractor, you need to be absolutely aware of what you are contracted to do and what your duties and obligations actually are. He adds that a contractual claim is an expected process under any contract and should not automatically end in dispute.

    “Many cases are doomed because parties fail to consider properly if in fact an entitlement exists under the contract,” he says. “A disgruntled party can be blinded and become entrenched in personal pride, pursuing notional ex gratia or ‘equitable’ payments to recover his losses, where these really have no merit under the contract. He simply has not done what it was he was supposed to do.”

    John insists that unless entitlement is firmly established from the outset of a dispute, the claimant may be throwing good money after bad by pursuing a notional entitlement.

    “If you are in fact to blame, admit it to yourself first, then admit it to others, then take your medicine, accept your losses and move on with your life. The alternative could be a very expensive waste of time.”

    Once entitlement is established the client has a formidable force on their side

    And if John feels a client needs to receive this kind of message, he will advise them honestly and bluntly: “What we do involves being very straightforward in our advice on this.”

    John believes that the success of John Farage O’Brien lies in the company’s ability to start from a firm base, to ascertain if an entitlement exists, and to quantify the likelihood of recovery.

    Once entitlement is established, however, the client has a formidable force on their side. John Farage O’Brien sets about building the case from the ground up, founded on clear facts supported by hard evidence. The company sets out to maximise the client’s chance of success in the negotiating forum, and in all cases has succeeded in this.

    The company’s success record is enviable — and envied.

    John O’Brien has a fundamental belief that in life people can generally be separated into two distinct groups, those with integrity and those without. He has found that this division has given rise to many of the disputes he has been involved in over the years

  • Getting the adversary factor out of disputes

    Getting the adversary factor out of disputes

    [siteorigin_widget class=”SiteOrigin_Widget_Headline_Widget”][/siteorigin_widget]

    Taking the ‘adversary factor’ out of disputes and disagreements: Conciliation conference

    Preparing for a conciliation conference

    THE TERM ALTERNATIVE dispute resolution embraces only those methods of resolving disputes that do not involve court action, so it employs processes such as adjudication, arbitration, conciliation, and mediation. 

    John Farage O’Brien are expert in all these methods and in supporting legal teams with specialist advice

    ADR yields many benefits, which range from far greater flexibility in procedures, costs normally way below those of traditional litigation, and speedy resolution of disputes as long as the parties to the dispute are committed to engage in a meaningful way.

    A very clear benefit of ADR in comparison to court proceedings is privacy and confidentiality. While court cases are open to the public and proceedings may be published, all dispute resolution proceedings take place in private, behind closed doors, and parties are generally bound by non-disclosure clauses in any settlement.

    We take strategic considerations fully into account: for us, these play an important part in deciding how to handle disputes, so we provide strategic analyses to clients where a case may have effects and consequences beyond the immediate issue or in the longer term.

    This is the fifth field, which director John FFF O’Brien describes as ‘political’, in the sense that experienced directors may need to make decisions on the final resolution of a dispute which can reap a long term benefit for the company in spite of immediate sacrifices — akin to “losing the battle to win the war”.

    ADR is widely used in commercial contracts. Parties to contracts often find themselves prevented from proceeding to Court by being ‘stayed’ to refer their dispute under contract to binding arbitration which has been expressly agreed by the parties, sometimes without realising it, at the time of contract. Arbitration clauses have become almost universal in all standard forms of construction contract and are usually preceded by a mandatory, step-down conciliation or mediation process before proceeding to full arbitration.

    Mediation is fast becoming the norm for parties to resolve their differences, and to do so with the aid of a third party who helps the disputants to actively identify for themselves where the resolution may lie. When a party to a mediation truly identifies where the dispute lies, and identifies what is important to the other party, an agreed settlement will usually follow.

    “Directors may need to make immediate sacrifices in the final resolution of a dispute, in order  to reap a long term benefit for the company — akin to losing the battle to win the war

    The Irish courts fully endorse mediation, and where one party is approached by the other to attempt to mediate a dispute but fails to do so, that party could find itself losing its costs, even if it succeeds ultimately in court. The parties in dispute must agree to use one or more of these processes, either before or after a dispute has arisen. John Farage O’Brien are expert in all these methods and in supporting legal teams with specialist advice.

    How to get the ‘adversary factor’ out of disputes and disagreements

  • Why are construction disputes so complex?

    Why are construction disputes so complex?

    Why Are Construction Disputes Almost Never Straightforward?

    That’s the big question that comes up most among our clients, colleagues and advisors

    Buildings and cranes against sunset — complex
    Buildings and cranes against the sunset

    CONSTRUCTION DISPUTES are inherently very complex to resolve because they usually cross over several professional disciplines, to varying degrees and with varying weightings for each of these, depending on circumstances.

    If there is a deficit in knowledge, appreciation, understanding and practical experience of any of these separate disciplines, this can quickly give rise to areas of doubt and uncertainty.

    This can lead parties to seek external advice from consultants, lawyers and experts — in many cases solely to justify an entrenched position.

    Many parties to a dispute can find themselves deep into an alternative dispute resolution process, looking for an entitlement that may not exist in reality.

    But a party armed with the benefit of weighted, expert advice across all disciplines will increase enormously its chances of early resolution or of avoiding unnecessary proceedings.

    John Farage O’Brien is one of the few consultancies which can provide this advice to a consistently high standard, with qualifications, expertise and experience in all relevant disciplines.

    Why are construction disputes often so terribly complicated? That’s the big question that comes up most among our clients, colleagues and advisors

  • When those in dispute go to war

    When those in dispute go to war

    After 14 years as a contract claims consultant and advocate, managing construction disputes for clients amounting to a total of €2.5 billion in project value, and acting as an arbitrator and conciliator, John O’Brien reflects on the lessons learned

    John O'Brien
    John O’Brien

    IT NEVER CEASES TO AMAZE ME that many of the professional people I meet have no idea that some of the biggest commercial contract disputes in this jurisdiction are fought, settled or decided behind closed doors. I recall at least one lawyer making the cringe-worthy statement that “if one fails to settle in Arbitration, one can always go to court”.

    Wrong. You Can’t

    This is the reality of alternative dispute resolution (ADR) — all hearings, whether conciliation, mediation, arbitration or adjudication, take place behind closed doors and in total confidence, with no public access, no reporters, and gagging clauses common. No ‘verdicts’ are published — in fact, only the parties to a dispute and their representatives are aware of the existence of the dispute.

    The confidentiality of the ADR process is something that we as professional practitioners are obliged to take very seriously. But confidentiality brings both positive and negative effects, not just for parties to the process but the construction industry at large.

    The positive effects are, firstly, that parties can wash their dirty linen safe in the knowledge that the public will never know the outcome of the dispute nor their private business and its commercially sensitive information.

    Secondly, ADR has the benefit of having a construction industry expert sitting in the chair to assist in resolving disputes in this most complex field.

    Thirdly, the final, heavy-duty tier of ADR is arbitration, and it is both final and binding. The dispute is over. No appeal, no challenges and, most important, no additional costs to the parties (the only exception being in a very limited set of circumstances of misconduct by the Arbitrator, for which there has yet to be a successful application to the High Court under the 2010 Arbitration Act). Arbitration gives closure to commercial entities in dispute, allowing them to move on with their business.

    Negative Consequences

    But l’ve also seen instances of negative consequences from this in camera system, and I group them under two headings:

    Firstly, the ADR process loop is never closed — unlike a dispute that has been referred to court and where a judgment has been published. In such circumstances, the court’s control loop is essentially closed where published judgments permit sub-contractors, main contractors and employers to evaluate the standing of their dispute in law. This allows the aggrieved party to consider if there really is a cause of action, and if not, it can stand down its army and retreat before wasting a lot of time, effort and money. With ADR, there is no publication of either judgment or argument.

    Secondly, ADR is open to abuse by respondents with deep pockets who can avoid public accountability and possible reputational damage behind the closed doors of the arbitration chamber.Such respondents may, for example, deploy strategies of frustration in order to deplete the war chests of even the strongest of claimants and try and beat them into commercial surrender — regardless of how strong their entitlement is.

    [  Read more >>  ]

    Many of the professional people I meet have no idea that some of the biggest commercial contract disputes in this jurisdiction are fought, settled or decided behind closed doors.