Tag: John FFF O’Brien

  • Covid-19: Ex Gratia Payments and Public Works Contracts

    Covid-19: Ex Gratia Payments and Public Works Contracts

    You may recall my comments in May last year when the OGP first published guidance in relation to Employers making ex gratia payments to Contractors for costs associated with the stoppage of works and closure of sites. I both started and finished with the line:

    Private contractors on public works contracts do not get gifts or favours from the government.

    Having considered the OGP’s latest publications on the ‘Covid Co-operation Framework’, which proposes ex gratia payments for the costs of implementing measures on construction sites required under the ‘Return to Work Safely Protocol’, the sentiment in that line still remains valid.

    The Current Position

    First, let’s take stock of the current position: there are now two ex gratia relief mechanisms offered on a ‘without prejudice’ basis to contractors who entered into Public Works Contracts before the occurrence of Covid-19.

    The first of these provides a contribution from the Employer to the Contractor for their costs of demobilisation, securing the site and prolongation costs, where these result directly from the stoppage of non-essential works and closure of sites due to Covid-19.

    The second ex gratia relief provides a contribution from the Employer to the Contractor for: (1) the costs of re-mobilising and getting back to work after the Covid-19 suspension, and (2) the costs for carrying out the remaining contract works under heavily disrupted [socially distanced] conditions, collectively labelled “the Return to Work Safely Protocol” (the ‘Protocol’).

    Construction site

    First Ex Gratia Payment Relief

    In my opinion, the stoppage of works and closure of sites in respect of non-essential works results in a suspension to the works that Employers’ were obliged to instruct in compliance with directions from Government. Do not forget, the direction from the office of the Taoiseach at the time was that Employers were to decide whether or not works were ‘essential’ and to inform Contractors of this.

    It follows, if Employers decided that works were non-essential and communicated this to Contractors as they should have, this amounts to a de facto instruction to suspend the works. That instruction then falls squarely within Event 3 Part K of the Tender and Schedule entitling the Contractor to time and money. Event 3 reads as follows:

    “The Employer’s Representative directs the Contractor to Suspend the works under sub-clause 9.2.”

    The OGP has sought to avoid this issue and has instead suggested that the closure of sites and stoppage of works was an Event 15 under Part K of the Tender and Schedule entitling the Contractor to time only.

    Event 15 reads as follows:

    “Delay to the Works caused by the order or other act of a court or other public authority exercising authority under Law.”

    I do not agree with the OGP’s position that the closure of sites and stoppage of works qualified as an Event 15. This is for a number of reasons:

    • First, as set out above, as a matter of fact, in compliance with directions from government, it was for Employers to decide whether or not works were essential and to inform Contractors. Where this process was not followed in respect of non-essential works, it is simply Employers seeking to shirk responsibility and avoid having to give both time and money pursuant to Event 3.

    Unfortunately, the OGP’s stated position gives misplaced credibility to Employers that did not follow the process that was envisaged by the Department of the Taoiseach.

    • Second, the OGP’s logic that the suspension falls within Event 15 at all, is incorrect. This is because, plainly, it was not “the introduction of a law or the order or act of a court or other public authority” that “caused” the delay to the works – what actually caused delay to the works was the occurrence of a global pandemic and the subsequent outbreak of the illness in Ireland.

    The pandemic itself is the root cause of the delay, not any law or order brought about as a result of it. The introduction of laws or orders made to deal with the pandemic are a secondary matter, which the OGP is seeking to rely upon in order to shoehorn site closures and stoppages of works into Event 15.

    • Third, and following on directly from my second point, in any event the Regulations made by the Minister for Health which underpinned the Taoiseach’s announcement with regard to the closure of sites were not introduced until after sites were closed and until after the instruction by the Employer with regard to suspension of the works should have been given.

    The OGP cannot therefore properly rely on the making of those regulations as a basis for shoehorning the suspension into Event 15, since the Regulations only came into effect after suspension occurred.

    Public sector Employers’ and the OGP’s approach in relation to this matter can be seen as even more cynical when viewed from the perspective of the indemnity provided by the Employer to the Contractor pursuant to sub-clause 3.5(1) of the Contract.

    That indemnity is for “liability for death, injury, or illness of any person or loss of or damage to any physical property that the Contractor incurs in the course of performing the Contract to the extent caused by the negligence of the Employer”.

    Considering the breath of this indemnity, which obviously encompasses issues that might arise as a result of Covid-19, the Employer should have taken immediate and appropriate action to instruct the suspension the works.

    Unfortunately, this is not what occurred in practice, with many Employers leaving it to the Contractor or the Employer’s Representative to take action independently, notwithstanding a direction from Government that it was for the Employer to take such action.

    Second Ex Gratia Payment Relief

    The second ex gratia relief relates to costs incurred by Contractors in implementing measures on construction sites to comply with the Return to Work Safely Protocol.

    This time, the OGP has decided that compliance with the Protocol is now not even an Event 15. Its position has hardened and it now states that the Contractor is neither entitled to time nor money in completing its works in compliance with the Protocol:

    “The OGP considers that the standard forms of Public Works Contracts (PWC) do not provide an entitlement to Contractors to an extension of time or to recover any costs that may arise as a result of the introduction of the Protocol and/or the implementation of the Protocol Measures.”

    I do not agree with the OGP’s stated position that the implementation of the measures to comply with the Protocol on construction sites does not give rise to any entitlement under the Contract.

    My view is that the compliance with the Protocol is, at its most basic, an additional constraint on the works that gives rise to an Event 1 under Part K of the Tender and Schedule (a Change Order) which entitles the Contractor to both time and money.

    Notwithstanding its stated position, the OGP also notes that the ex gratia payments agreed under the proposed framework for dealing with the implementation of measures pursuant to the Protocol are to help to “ease the financial burden on Contractors”. This is, again, a cynical statement, given that any ex gratia payments will be limited to a maximum of 50% of the Contractor’s actual costs, but ‘only’ on the basis that the Employer’s budget allows it to pay out even that.

    Consequently, the absolute best that Contractors can even hope to obtain is 50% of their costs, but will likely get far less with Employer’s seeking to rely on restricted budgets as the reason for not being in a position to pay out.

    OGP Overall Strategy

    The ex gratia payment reliefs, taken together, are no more than the OGP seeking to support Public Sector Employers in attempting to get a better deal by agreeing to make payments to Contractors at a lower level than those to which Contractors’ are actually entitled.

    It is the difference is between charity and entitlement, and prudent Contractors should seek to exercise their entitlement if as good as, or a better deal, is not on the table under the ex gratia payment procedures.

    Furthermore, Contractors need to bear in mind the additional barbs included in the ex gratia payment mechanisms, which would make it unattractive to bring claims after agreeing to take ex gratia payments – these include the Employer obtaining “open-book” access to Contractor’s costs and records, and the ability to claw back any ex gratia payments made should the Contractor be successful in a claim.

    The OGP’s ex gratia relief and payments are, on the one hand, a proactive initiative to restart works and get back to work safely, whilst on the other, an initiative to reduce the Government’s potential exposure, by creating the ‘lesser of two evils’ option, inducing Contractors into agreeing ‘settlement payments’ in exchange for a waiver by the Employer to imposing Liquidated Damages for delay.

    This OGP initiative may suit some Contractors who have substantially weathered the storm, with the assistance of the Covid-19 weekly wage subsidy to their staff, and now simply want to get back to work, but to other contractors these ex gratia relief charitable offers will simply not be enough to cover the shortfall and losses. As a result, they will have no choice but to pursue their full compensation entitlement.

    6 August 2020

    You may recall my comments in May last year when the OGP first published guidance in relation to Employers making ex gratia payments to Contractors for costs associated with the stoppage of works and closure of sites. I both started and finished with the line: Private contractors on public works contracts do not get gifts or favours from the government.…

  • Covid-19: Public Works Contracts and ‘Ex Gratia’ Payments

    Covid-19: Public Works Contracts and ‘Ex Gratia’ Payments

    PRIVATE CONTRACTORS on public works contracts do not get gifts or favours from the government. For this reason, the publishing by the Office of Government Procurement (OGP) of a draft letter of agreement dealing with ‘ex gratia’ payments from Employers to Contractors can only be cautiously welcomed.

    For reasons that I am sure you are well aware of, which include, inter alia, the indemnity provided by employers for negligence causing illness or death under Clause 3.5, this action by the OGP is not unexpected. However, you can be sure that these ‘ex gratia’ payments will not cover the full extent of employers liability to contractors now, or for the many months to come long after 4th May 2020 when the country, slowly and progressively, gets back to work — which will certainly not be under the same conditions that the work was tendered or contracted upon.

    As a general point, I am minded to conclude that this move by the government, to offer any ex gratia payment, is the genesis of setting an acknowledgement (or dare I say) precedent in paying compensation to contractors of their actual prolongation losses, which is in contrast to the normal denial under the controversial tendered schedule 2D daily delay rate.

    Contracts page: Contract document with magnifying glass

    With regard to the specifics of the OGP’s ‘Model Form Supplemental Agreement’, entitled ‘Public Works  Contracts Covid-19 EX-GRATIA PAYMENT BY THE EMPLOYER LETTER AGREEMENT v1.0’ published on April 23, I comment as follows:

    Entitlement to Delay Costs

    I disagree with the employer’s assertion at Paragraph 4 that the contract does not provide an entitlement for the contractor to recover costs associated with the delay arising from the closure of the site in the circumstances  contemplated  by  the  Public  Health Measures.

    If the employer was correct in his assertion in this regard, then the employer’s position would simply be that the Covid-19 pandemic is a Part 1 Schedule K Event 15, and would give time but no money. Hence, any payment would be a genuine ex gratia gift.

    There exists a very important aspect that does not make this pandemic a Part 1 Schedule K Event 15 — which carries a Yes/No designation to delay and compensation — and  this  is  that  the  Office  of  the Taoiseach  decided  that  each  employer  (public  and private) had to decide for themselves, [not the government nor not by any act or law] whether their site or project was essential or non-essential and whether to remain open or not1.

    Therefore, if the site was to remain open, then it could only do so under the disruption of social distancing constraints, (which could not be denied by the employer under the risk of the indemnity given under clause 3.5), and a change in the manner of how works are to be executed and a requisite EoT would apply by way of change order Part 1 Schedule K Event 1, which carries a Yes/Yes designation to delay and compensation.

    Or, if the site was to be closed, then the works could only be suspended under Part 1 Schedule K Event 3, which carries a Yes/Yes designation to delay and compensation.

    That being so, this ex gratia payment is a welcome gift but will be offset against the actual costs that contractors will seek to claim, and should claim.

    Opening the Kimono

    Paragraph 3(a) (i) & (ii) needs to be, and will be, approached with extreme caution by contractors.

    For the purposes of the employer, or the party nominated on its behalf, determining the amount of ex gratia payment the contractor has to:

    (i)  provide a complete and full breakdown of the contract preliminaries on a transparent and “open book” basis; and [represent and warrants that]

    (ii)  it has made all its records, supporting and vouching material available”

    Whilst a claim for prolongation loss and expense, is generally the remedy for critical delay caused by an employer culpable event under a standard form, to put the contractor back into the financial position it was in before the event or breach occurred, even in arbitration, disclosure or discovery is not carried out on an “open book” basis to prove such loss. Supervised inspection, of agreed categories of discovery, or relevant categories directed by an arbitrator is the norm, but not an open-ended free for all for opposing parties to indulge.

    “Open book” is a completely undefined term in the supplemental agreement letter, and if signed by a contractor, then the definition would come down to whatever the employer required in order to satisfy its curiosity.

    “All its records” is another completely undefined term in the supplemental agreement letter, and if signed by a contractor, could expose it to the whims of overeager ER.

    Furthermore, the OGP Update 1 dated 14 April 2020, Section 4 “Calculating Ex-gratia Payments” sets down a completely obscure formula that in no way produces a figure, which would compensate the contractor for its actual losses as a result of Covid-19.

    Unacknowledged Future Costs

    At Paragraph 3 (c) the employer seeks to limit his exposure to liability with regard to the denying of any ex gratia claim / payment for supervisors (individuals) who have left employment in connection with the works, or have been laid off since 28 March 2020. While this might be the employer’s prerogative to do so, as he is the one issuing a “gift”, the cost of a supervisor or any individual that had to be laid off or made redundant; and

    the consequential costs of re-employing individuals — which may include an increase from a price fluctuation in wages — may very well form part of the substantive claim for compensation which the contractor will be entitled.

    Payments are ‘Final and Binding’

    Paragraph 4 states that the decisions of the employer, relating to the ex gratia payment “including the amount and make-up of it are final and binding”.  Is final and binding forever? Or just until, for example, the employer decides he has paid too much ex gratia under paragraph 7?

    To me, this seems to be a moot point since any sums that contractors do not recover through the ex gratia payment will likely form part of a claim under the contract. The nature of the ex gratia payment being final and binding is therefore partially irrelevant.

    Site Closure Costs

    At Paragraph 6, the employer expressly distances itself from any liability or responsibility in respect of “Site Closure Costs”. These costs and their relationship with the contract are kept deliberately vague. In particular, the relationship between site closure costs and  compensation  under  a  suspension  pursuant  to Part One schedule K Event 3 is entirely avoided. This is a glaring absence.

    By the contractor signing up to the supplemental letter (purportedly extending the entire agreement) is he now essentially accepting that the ex gratia payment (gift) is in fact the site closure costs? When in fact, they most certainly cannot be — especially in the manner in which the employer calculates the ex gratia payments, under Section 4 of the OGP Update 1 dated 14 April 2020.

    Claims, Maintaining Entitlements and Clawbacks

    Paragraph 7 states: “If the contractor makes any claim under the contract or otherwise against the employer in connection with the Public Health Measures or the Regulations, and is successful in such claim, the amount payable to the contractor as a consequence of such claim shall be reduced by the amount of the ex gratia payment.”

    This clause is interesting in that it specifically acknowledges the ability of contractors to make additional claims for money on top of whatever is agreed as an ‘ex gratia’ payment. In order that contractors maintain their entitlements so that they can pursue such claims, I would advise all contractors to raise 10.3 notices now in respect of their actual costs, and or notify the ongoing costs, to protect themselves from any attempt at an employer time bar further down the road.

    ‘Public Health Measures’, while published by gov.ie, do not change the fact that the Covid-19 pandemic has not been classified nor does it meet the criteria of a part One Schedule K Event 15, and it is for the employer — the government — under a public works contract, to either suspend the works under an Event 3, or to instruct continuance at social distancing and or other imposed constraints on the manner in which the works are executed under Event 1 — both circumstances entitling the contractor time and compensation.

    I see a potential sting in the scorpion’s tail of the supplemental agreement (letter) in the second part of Paragraph 7, which states:

    “And in the event the ex gratia payment exceeds the amount determined is due to the contractor in connection with such claim, the contractor shall pay to the employer the amount of such excess within 10 days of such amount being demanded.”

    If the employer determines, wrongly in my view, that any such other claim in connection with the public health measures, that the Schedule 2D where a contractor has tendered a €zero daily rate applies, will the contractor then have to give the entire ex gratia payment back to the employer?

    Private contractors on public works contracts do not get gifts or favours from the government.    

    28 April 2020


    1 Also, Section 3 of the OGP Update 1 dated 14 April 2020 so stipulates

    PRIVATE CONTRACTORS on public works contracts do not get gifts or favours from the government. For this reason, the publishing by the Office of Government Procurement (OGP) of a draft letter of agreement dealing with ‘ex gratia’ payments from Employers to Contractors can only be cautiously welcomed. For reasons that I am sure you are…